Measure›Data connect KESTREL FREIGHTRM
Assistant
Which of our sites is best suited to a renewable energy project, and why? What type of project? Can you help us shortlist some ideas?
Read half-hourly demand for 5 sites · 2 tool calls
Checked roof assessments and available area
Pulled 12 months of Meridian invoices for the tariff
Modelling yield and self-consumption per site
Show agent trace · 10 tool calls · 5 iterations
For Kestrel Freight, the strongest first candidate is Daventry Hub. It used 4,173,832 kWh in the last financial year, making it by far the largest single consumer in the network.[2] Roof assessment indicates room for about 553 kW of rooftop PV, generating roughly 463,136 kWh a year — around 11% of its demand.[5]
Why it stands out
Refrigerated cross-dock running 24/7, so nearly all the generation is self-consumed rather than exported.
18,400 m² of flat warehouse roof with good orientation and full assessment coverage.
Your EV charging rollout lands here first, so PV should be sized alongside the grid connection upgrade rather than as a standalone array.
Suggested next step
Treat Daventry Hub and Avonmouth Cross-dock as the two investment candidates, and Solihull Head Office as the visible, customer-facing project. On your current tariff of 24.6p/kWh — taken from the invoices already in Earthchain — that displaces about £96,400 of the site's £1.14m annual electricity bill. I've put the shortlist, the demand comparison and an indicative business case in your workspace.
Half-hourly demand · 5 sitesRoof assessmentInvoiced spend · 12 monthsModelled estimates, not metered output
Ask a follow-up…
Workspace
Export
Renewable project shortlistREADY
SiteAnnual kWhIndicative PVkWh/yrBest project concept
Daventry Hub4,173,832553 kW463,136Solar PV + battery + EV charging integration
Avonmouth Cross-dock1,118,382342 kW336,213Solar PV + battery + refrigeration optimisation
Wakefield Depot699,06041 kW39,245Rooftop PV + lighting and dock-door controls
Solihull Head Office134,35548 kW39,199Rooftop PV + customer-facing display
Bellshill Depot302,907Not yet assessed—Assess roof condition and lease term before shortlisting
Demand vs modelled generationDemandGeneration
Daventry
Hub
Avonmouth
Cross-dock
Wakefield
Depot
Solihull
Head Office
Bellshill
Depot
Indicative case · Daventry Hub
Self-consumed92%
Electricity spend now£1,142,000/yr
Annual saving£96,400 · 8.4%
Capital cost£608,000
Simple payback6.3 years
CO₂e avoided94.9 t/yr
Spend taken from your Meridian invoices at 24.6p/kWh. Generation modelled from half-hourly demand and roof assessment — not a design or a quotation.